Why is it important to align the Work Breakdown Structure (WBS) and Cost Breakdown Structure (CBS)?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

Aligning the Work Breakdown Structure (WBS) and the Cost Breakdown Structure (CBS) is crucial primarily for traceability and accurate roll-ups. The WBS serves as a hierarchical decomposition of the project into smaller, manageable components or work packages. Each of these components can then have associated costs allocated to them as defined in the CBS.

When both structures are aligned, it allows project managers to effectively trace costs back to specific work packages. This traceability ensures that project costs can be aggregated reliably and that any variances from the budget can be accurately identified and addressed at the appropriate level of detail. Furthermore, accurate roll-ups are essential for monitoring overall project performance, synthesizing data, and reporting to stakeholders. By maintaining this alignment, project teams can provide a clearer picture of financial health throughout the project lifecycle, enabling better decision-making and management of resources.

Having the WBS and CBS aligned does contribute to better stakeholder communication, resource allocation, and potentially managing costs, but the primary advantage lies in ensuring that costs can be traced and rolled up accurately for effective project control.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy