Which three elements are identified as primary project constraints?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

The primary project constraints are often referred to as the "triple constraint," which includes scope, time, and cost. Collectively, these three elements form the foundation of project management.

Scope defines what is included and excluded in the project, essentially outlining the boundaries of the work that must be accomplished. Time refers to the project schedule, indicating how long the project is expected to take. Cost includes all financial resources required to execute the project. Each of these elements interacts with one another; for example, an increase in the scope may lead to an increase in time and cost, while completing the project faster could require more resources or could compromise the project's quality.

Understanding and balancing these three constraints is critical for project success and is a fundamental principle in project management methodologies.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy