Which term is defined as a constrained resource that drives scheduling?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

The term that is defined as a constrained resource that drives scheduling is a bottleneck resource. In project management and scheduling, a bottleneck resource is one that has limited capacity compared to the demand placed on it. This limitation affects the overall throughput of the project. When a resource is identified as a bottleneck, it can significantly influence the project schedule, as it represents the maximum amount of work that can be processed.

Focusing on a bottleneck allows project managers to prioritize tasks that utilize this critical resource in order to optimize the overall project timeline. Managing bottleneck resources effectively is crucial for ensuring that projects stay on track and deadlines are met. Resources that are not constrained do not have the same level of impact on scheduling and overall project flow.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy