Which of the following represents the four relationship types in a logic diagram?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

The correct answer highlights the four primary relationship types used in logic diagrams, which are crucial for effective project planning and scheduling. The relationships are:

  1. Finish-to-Start (FS): This is the most common relationship type, where a successor task cannot start until the predecessor task has finished. For example, a task of "pouring concrete" (predecessor) must be completed before the next task of "starting interior work" (successor) can begin.
  1. Start-to-Start (SS): This type indicates that a successor task can start only after the predecessor task has started. An example would be starting "drywall installation" when "framing" begins, rather than waiting for framing to finish.

  2. Finish-to-Finish (FF): Here, the completion of a successor task is dependent on the completion of its predecessor task. For instance, the task "final inspections" (successor) cannot finish until "all construction" (predecessor) is completed.

  3. Start-to-Finish (SF): This is a less common relationship where a successor cannot finish until the predecessor has started. For example, if a night shift worker's task cannot be completed until a day

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy