Which of the following is a defining trait of non-excusable delays?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

A defining trait of non-excusable delays is that they originate from contractor fault. This type of delay typically results from actions or inactions by the contractor that hinder the progress of the project but are not attributed to outside influences or unforeseen circumstances. Non-excusable delays do not qualify for time extensions and the contractor is held accountable for the impact of these delays on the project schedule.

In project management, it is crucial to differentiate between types of delays—the key is understanding the responsibility assigned to the contractor. Non-excusable delays directly implicate the contractor's performance and responsibilities as they relate to achieving project milestones.

The other choices do not accurately reflect the definition of non-excusable delays. A time extension being guaranteed pertains more to excusable delays that are recognized as being beyond the contractor's control. Delays benefiting the project timeline may not even constitute delays in a traditional sense, while delays caused by external circumstances are generally classified as excusable and do not fit within the bucket of non-excusable delays. Thus, the recognition of contractor fault as a characteristic of non-excusable delays is essential for effective scheduling and project accountability.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy