Which MIPs do not require the insertion or removal of fragnets?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

MIPs, or Methodologies for Integrating Project Schedules, are essential in planning and scheduling, particularly in how they manage various project elements like fragnet insertion and removal.

The correct choice highlights MIPs 3.1, 3.2, and 3.6. These specific MIPs focus on refining the project's overall schedule and enhancing accuracy without necessitating the more complex process of inserting or removing fragnets, which are often used when dependencies or changes in project scope arise. This process can complicate project management significantly, especially when it involves adjusting timelines and resources substantially.

MIP 3.1 is typically associated with establishing proper sequencing of tasks, while MIP 3.2 emphasizes the maintenance of a baseline schedule. MIP 3.6 generally addresses performance metrics and tracking, which can be accomplished without altering the structural components of the schedule through fragnet adjustments.

In contrast, the other options include MIPs that involve activities or calculations that would inherently require such insertion or removal of fragnets. Understanding the nuances of these MIPs is crucial for effective project scheduling and management, highlighting the importance of selecting the right methodologies based on project needs.