What type of delays does a contractor experience during concurrent delays?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

Concurrent delays refer to situations in a project where two or more delays occur at the same time, but are caused by different parties. This can include delays from the contractor, owner, or subcontractors, and they can impact various aspects of the project.

When a contractor experiences concurrent delays, it is essential to recognize that these delays do not arise from a single source but rather from multiple influences happening simultaneously. This dual impact can complicate the assessment of responsibility and recovery options since each party may have caused certain delays that overlap with others.

This understanding also plays a critical role in contractual claims and disputes, as it can affect liability and entitlement to time extensions or compensation. Recognizing the nature of concurrent delays is important for project managers and schedulers in accurately determining how these delays affect the project timeline and how to address them effectively. The concept emphasizes the complexity of managing projects where multiple factors contribute to schedule disruptions at the same time.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy