What is typically required for baseline submittal?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

For a baseline submittal in project planning and scheduling, certain documentation and details are essential to provide a clear and structured representation of the project plan. The correct answer highlights the need for a narrative, logic report, activity coding, and milestones, all of which play critical roles in establishing a comprehensive baseline.

The narrative provides context and details about the project, outlining its scope, objectives, and key assumptions. This contextual information is vital for understanding the plan’s framework. A logic report illustrates the interrelationships between tasks and their sequences, offering insight into how activities are interconnected and how they contribute to the overall schedule. Activity coding helps in organizing tasks in a systematic way, making it easier to track progress and manage resources effectively.

Milestones represent significant events or checkpoints in the project timeline. They help to measure progress and facilitate stakeholder communication. By including these elements in the baseline submittal, stakeholders can effectively review, approve, and monitor the project plan throughout its execution.

In contrast, the other choices contain components that, while relevant to project management, do not specifically pertain to the requirements for a baseline submittal. For example, risk assessments and financial analyses, while important for overall project planning, are not typically required at the baseline stage. Daily