What does the term 'data date' refer to in schedule analysis?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

The term 'data date' refers specifically to the cutoff point for progress measurement in schedule analysis. This date serves as a reference point for evaluating the project's current status, capturing all activities and their progress up to that point. By establishing a data date, project managers can analyze completed tasks, ongoing activities, and any delays relative to the planned schedule.

Choosing this date allows for a more accurate assessment of where the project stands concerning its timeline and milestones. It informs stakeholders about how much work has been accomplished and helps identify any discrepancies between planned and actual performance, guiding necessary corrective actions.

In contrast, the other options do not accurately reflect the definition of 'data date': the starting point for project analysis is typically defined when the project begins, while the deadline for project completion is set as part of project planning, and the date of the project kickoff specifically marks when the project formally starts rather than serving as a reference point for progress tracking.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy