What does it imply if a delay is categorized as excusable?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

Categorizing a delay as excusable implies that the contractor may be eligible for a time extension due to uncontrollable factors. Excusable delays are typically those beyond the control of the contractor, such as adverse weather, acts of God, or changes in law that impact the project's timeline. When such delays occur, the contractor is not held liable for the costs associated with them, as they are not due to the contractor's negligence or failure to perform.

In these cases, the contractor often needs to formally request a time extension, demonstrating that the delay was indeed excusable and not caused by their own actions. This allows the project to maintain its integrity by accounting for unforeseen circumstances that may affect scheduling without penalizing the contractor for factors they could not influence.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy