What does excessive float in a schedule usually indicate?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

Excessive float in a schedule typically indicates illogical sequencing or unrealistic durations. When a project schedule has an abundance of float, it suggests that the relationships between tasks may not be well thought out, leading to an overestimation of available time for certain activities. This can occur when tasks that are dependent on each other lack a clear logical flow or when durations assigned to specific tasks do not accurately reflect the work required to complete them.

For instance, if tasks are sequenced in a way that does not align with the project's critical path, it can create unnecessary float. Similarly, if durations are assigned too liberally, this may result in more float than is practical or realistic. While some float is a normal and expected part of project scheduling, excessive amounts can signal underlying issues that may affect the project's timeline and efficiency. Properly analyzing and adjusting task relationships and durations can help in minimizing excessive float, leading to a more realistic and efficient schedule.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy