What does early start (ES) refer to in scheduling?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

Early start (ES) refers to the earliest time an activity can begin in a project schedule without being delayed by preceding activities. This concept is essential in project management and scheduling because it helps determine the flow of operations and the overall timeline of the project.

In developing a project schedule, each activity is analyzed along with its dependencies on other activities. The early start time is calculated based on the earliest finish of any predecessor activities. By knowing the early start, project managers can optimize the sequence of tasks, identify critical paths, and effectively allocate resources.

Understanding early start is crucial for effective planning and scheduling. It enables a project manager to assess the feasibility of timelines and make informed decisions on scheduling practices to meet project deadlines.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy