What does EAC represent in project management?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

EAC, or Estimate at Completion, is a crucial term in project management that represents the forecasted total cost of the project at completion. It is derived from performance data gathered throughout the project’s lifecycle and serves as an essential tool for project managers to gauge future spending and financial health.

By calculating EAC, project managers can take into account variances in costs and project progress, adjust budgets accordingly, and make informed decisions to steer the project back on track if necessary. EAC enables proactive management of project finances, ensuring that stakeholders have a clear understanding of the expected final cost compared to the original budget. This is particularly important for managing stakeholder expectations and for financial forecasting.

The other alternatives, while they represent important metrics in project management, do not accurately depict what EAC stands for. Actual cost incurred to date relates to costs already spent, the budgeted value of remaining tasks refers to the planned budgets for tasks not yet completed, and estimated time required to complete addresses the timeline rather than costs. Therefore, understanding EAC as a forecasted total cost is vital for effective financial management in projects.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy