What does a constraint override mean in project scheduling?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

A constraint override refers specifically to the situation where specific imposed dates take precedence over the dates that would normally be calculated based on the project's logical relationships and sequences. In project scheduling, tasks are typically sequenced in accordance with their dependencies, and the start and finish dates are derived from these relationships. However, when a constraint override occurs, it means that a hard date has been set (such as a contractual deadline) which will dictate when a task must start or finish, regardless of the established logical schedule. This can be a crucial element in managing timelines when external commitments or requirements are involved.

Understanding this concept is important for planners and schedulers, as it affects how they manage timelines and prioritize tasks, potentially leading to adjustments in logic or dependency relationships among tasks.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy