What defines a "driving relationship" in the context of project scheduling?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

A "driving relationship" in project scheduling refers to a logic link that directly controls an activity's timing. This means that it is a dependency where the start or finish of one activity directly influences the start or finish of another. In project management, understanding these relationships is crucial for creating a reliable schedule, as they help to determine the sequence of activities and their durations.

When an activity is dependent on another due to a driving relationship, any changes in the preceding activity's schedule will impact the subsequent activity. Therefore, accurately identifying driving relationships allows project managers to foresee potential delays and address them proactively, ensuring the schedule remains on track.

In contrast, the other options describe different types of relationships or dependencies that do not contribute to the critical path or overall project timing, such as those that do not impact the schedule or focus solely on resource allocation. Recognizing the significance of driving relationships is essential for effective planning and scheduling.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy