What constitutes schedule manipulation?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

Schedule manipulation refers to unethical practices where the schedule is intentionally altered to misrepresent the true status of a project, often to mislead stakeholders. This can involve changing the logic of the schedule, adjusting task durations, or modifying the status of tasks in order to create a false impression of progress or performance.

Choosing to adjust logic or status for deceptive purposes directly characterizes schedule manipulation, as it undermines the transparency and accuracy that are crucial in project management. This type of manipulation can significantly affect decision-making, resource allocation, and ultimately the success of the project, as stakeholders may base their decisions on incorrect information.

The other options, while they involve changes to the schedule, do not inherently involve deceit or misrepresentation. For example, adjusting resource levels to meet deadlines could be a legitimate project management practice aimed at optimizing resource allocation without intentionally misleading anyone. Similarly, changing schedules based on team feedback or revising project goals in response to budget changes can be part of normal, responsible project management adjustments, not manipulative actions aimed at misleading stakeholders.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy