What characterizes a non-excusable delay?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

A non-excusable delay is characterized by delays that occur due to factors that are within the contractor's control, thus not allowing for any time extensions or relief under the contract terms. In such scenarios, the contractor is generally responsible for managing the scheduling and performance of the project, leading to potential penalties or liquidated damages if delays occur.

A delay caused by contractor fault means that the contractor has not performed as per the contract specifications or has made decisions that have adversely affected the project timeline. Since this is a situation where the contractor could have taken actions to mitigate the delay, they bear the consequences of these delays without the opportunity for time relief.

This understanding is crucial for project management and contract administration, as it informs how parties should prepare for potential delays and the implications of poor performance or mismanagement of project resources.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy