What can be inferred about activities on a near-critical path?

Prepare for the AACE PSP Certification Exam with flashcards and multiple-choice questions. Enhance your knowledge with explanations and hints. Get exam ready today!

Activities on a near-critical path are those that are close to the critical path but are not currently critical themselves. Being near-critical means that these activities have little float or slack time, which indicates that any delays in them could potentially cause them to extend beyond their allowable time and shift the project's status to a critical path condition.

If a near-critical activity encounters delays or issues, it is likely to directly affect the project's overall timeline. Thus, it can be inferred that these activities are at risk of becoming critical. Staying vigilant and monitoring these activities closely is essential to prevent delays from cascading into more significant project management concerns. Since they play a crucial role in maintaining the project schedule, understanding their status helps ensure timely delivery and resource allocation.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy